Combined Rates

Calculate how long tasks take when multiple workers or machines work together.

Learn

Calculate how long tasks take when multiple workers or machines work together.

When multiple workers or machines work together, their rates add up. If Machine A produces 5 units/hour and Machine B produces 3 units/hour, together they produce 8 units/hour. To find time for a task, divide the total work by the combined rate. This also applies to pipes filling tanks or people completing tasks.

Combined Rate = Rate A + Rate B. Time = Total Work / Combined Rate

  • A makes 4/hr, B makes 6/hr → Together 10/hr → 50 units take 5 hours
  • Pipe A fills in 6 hrs, B in 3 hrs → Rates: 1/6 + 1/3 = 1/2 → Together: 2 hours
  • Worker A: 8 items/day, B: 12 items/day → 100 items = 100/20 = 5 days together

How to recognize it

  • Multiple workers/machines working simultaneously
  • Individual rates are given (units per time)
  • Asked for time when working together

Common mistakes

  • Averaging rates instead of adding them
  • Adding times instead of rates (if A takes 2hr and B takes 3hr, together is NOT 5hr)
  • Forgetting to convert to consistent rate units

Step-by-step walkthrough

Pipe A can fill a tank in 4 hours. Pipe B can fill the same tank in 6 hours. How long to fill the tank using both pipes?

  1. Calculate Pipe A's rate: 1 tank / 4 hours = 1/4 tank per hour
  2. Calculate Pipe B's rate: 1 tank / 6 hours = 1/6 tank per hour
  3. Add the rates: 1/4 + 1/6 = 3/12 + 2/12 = 5/12 tank per hour
  4. Calculate time: 1 tank / (5/12 per hour) = 12/5 = 2.4 hours

Answer: 2.4 hours (or 2 hours 24 minutes)

Practice guidance

Numerical Reasoning