Problemas de Rendimiento

Calcular el tiempo o los trabajadores necesarios cuando el trabajo total permanece constante.

Aprender

Calcular el tiempo o los trabajadores necesarios cuando el trabajo total permanece constante.

Work rate problems are based on the formula: Work = Rate × Time, or equivalently, Work = Workers × Days. If the total work is constant, increasing workers decreases time proportionally. The key insight is that 'worker-days' (or 'machine-hours') represents the total work, and this stays the same regardless of how many workers do the job.

Total Work = Workers × Time. If W1 × T1 = W2 × T2, then T2 = (W1 × T1) / W2

  • 4 workers in 12 days = 48 worker-days. 6 workers = 48 ÷ 6 = 8 days
  • 3 machines in 10 hours = 30 machine-hours. 5 machines = 30 ÷ 5 = 6 hours
  • 2 people in 15 days = 30 person-days. 5 people = 30 ÷ 5 = 6 days

Cómo reconocerlo

  • Problem mentions workers/machines and time to complete a job
  • Asks how long with different number of workers
  • Total work (job size) remains constant

Errores comunes

  • Thinking more workers means more time (it's inverse)
  • Adding workers instead of multiplying
  • Forgetting that work = workers × time

Resolución paso a paso

5 trabajadores completan un proyecto en 12 días. ¿Cuántos días tardarían 10 trabajadores?

  1. Calcula el trabajo total: 5 trabajadores x 12 días = 60 días-trabajador
  2. El trabajo total permanece constante en 60 días-trabajador
  3. Divide el trabajo total entre el nuevo número de trabajadores: 60 / 10
  4. Calcula: 60 / 10 = 6 días

Respuesta: 6 days

Orientación para practicar

Razonamiento Numérico