Arbeidstempo-problemen
Bereken de tijd of het aantal werkers wanneer het totale werk constant blijft.
Leren
Bereken de tijd of het aantal werkers wanneer het totale werk constant blijft.
Work rate problems are based on the formula: Work = Rate × Time, or equivalently, Work = Workers × Days. If the total work is constant, increasing workers decreases time proportionally. The key insight is that 'worker-days' (or 'machine-hours') represents the total work, and this stays the same regardless of how many workers do the job.
Total Work = Workers × Time. If W1 × T1 = W2 × T2, then T2 = (W1 × T1) / W2
- 4 workers in 12 days = 48 worker-days. 6 workers = 48 ÷ 6 = 8 days
- 3 machines in 10 hours = 30 machine-hours. 5 machines = 30 ÷ 5 = 6 hours
- 2 people in 15 days = 30 person-days. 5 people = 30 ÷ 5 = 6 days
Zo herkent u het
- Problem mentions workers/machines and time to complete a job
- Asks how long with different number of workers
- Total work (job size) remains constant
Veelgemaakte fouten
- Thinking more workers means more time (it's inverse)
- Adding workers instead of multiplying
- Forgetting that work = workers × time
Stapsgewijze uitwerking
5 werkers voltooien een project in 12 dagen. Hoeveel dagen zouden 10 werkers nodig hebben?
- Bereken het totale werk: 5 werkers x 12 dagen = 60 werkdagen
- Het totale werk blijft constant op 60 werkdagen
- Deel door het nieuwe aantal werkers: 60 / 10
- Bereken: 60 / 10 = 6 dagen
Antwoord: 6 days