Taux Combinés

Calculer le temps des tâches lorsque plusieurs travailleurs ou machines travaillent ensemble.

Apprendre

Calculer le temps des tâches lorsque plusieurs travailleurs ou machines travaillent ensemble.

When multiple workers or machines work together, their rates add up. If Machine A produces 5 units/hour and Machine B produces 3 units/hour, together they produce 8 units/hour. To find time for a task, divide the total work by the combined rate. This also applies to pipes filling tanks or people completing tasks.

Combined Rate = Rate A + Rate B. Time = Total Work / Combined Rate

  • A makes 4/hr, B makes 6/hr → Together 10/hr → 50 units take 5 hours
  • Pipe A fills in 6 hrs, B in 3 hrs → Rates: 1/6 + 1/3 = 1/2 → Together: 2 hours
  • Worker A: 8 items/day, B: 12 items/day → 100 items = 100/20 = 5 days together

Comment le reconnaître

  • Multiple workers/machines working simultaneously
  • Individual rates are given (units per time)
  • Asked for time when working together

Erreurs fréquentes

  • Averaging rates instead of adding them
  • Adding times instead of rates (if A takes 2hr and B takes 3hr, together is NOT 5hr)
  • Forgetting to convert to consistent rate units

Résolution étape par étape

Le tuyau A remplit un réservoir en 4 h. Le tuyau B en 6 h. Combien de temps ensemble ?

  1. Calculez le débit du tuyau A : 1 réservoir / 4 h = 1/4 par heure
  2. Calculez le débit du tuyau B : 1 réservoir / 6 h = 1/6 par heure
  3. Additionnez les débits : 1/4 + 1/6 = 3/12 + 2/12 = 5/12 par heure
  4. Calculez le temps : 1 / (5/12) = 12/5 = 2,4 heures

Réponse: 2.4 hours (or 2 hours 24 minutes)

Conseils de pratique

Raisonnement Numérique