Problemi di Resa Lavorativa

Calcolare il tempo o i lavoratori necessari quando il lavoro totale rimane costante.

Impara

Calcolare il tempo o i lavoratori necessari quando il lavoro totale rimane costante.

Work rate problems are based on the formula: Work = Rate × Time, or equivalently, Work = Workers × Days. If the total work is constant, increasing workers decreases time proportionally. The key insight is that 'worker-days' (or 'machine-hours') represents the total work, and this stays the same regardless of how many workers do the job.

Total Work = Workers × Time. If W1 × T1 = W2 × T2, then T2 = (W1 × T1) / W2

  • 4 workers in 12 days = 48 worker-days. 6 workers = 48 ÷ 6 = 8 days
  • 3 machines in 10 hours = 30 machine-hours. 5 machines = 30 ÷ 5 = 6 hours
  • 2 people in 15 days = 30 person-days. 5 people = 30 ÷ 5 = 6 days

Come riconoscerlo

  • Problem mentions workers/machines and time to complete a job
  • Asks how long with different number of workers
  • Total work (job size) remains constant

Errori comuni

  • Thinking more workers means more time (it's inverse)
  • Adding workers instead of multiplying
  • Forgetting that work = workers × time

Soluzione passo per passo

5 lavoratori completano un progetto in 12 giorni. Quanti giorni servirebbero a 10 lavoratori?

  1. Calcola il lavoro totale: 5 lavoratori x 12 giorni = 60 giorni-lavoratore
  2. Il lavoro totale resta costante a 60 giorni-lavoratore
  3. Dividi per il nuovo numero di lavoratori: 60 / 10
  4. Calcola: 60 / 10 = 6 giorni

Risposta: 6 days