Kombinierte Raten

Berechnen, wie lange Aufgaben dauern, wenn mehrere Arbeiter oder Maschinen zusammenarbeiten.

Lernen

Berechnen, wie lange Aufgaben dauern, wenn mehrere Arbeiter oder Maschinen zusammenarbeiten.

When multiple workers or machines work together, their rates add up. If Machine A produces 5 units/hour and Machine B produces 3 units/hour, together they produce 8 units/hour. To find time for a task, divide the total work by the combined rate. This also applies to pipes filling tanks or people completing tasks.

Combined Rate = Rate A + Rate B. Time = Total Work / Combined Rate

  • A makes 4/hr, B makes 6/hr → Together 10/hr → 50 units take 5 hours
  • Pipe A fills in 6 hrs, B in 3 hrs → Rates: 1/6 + 1/3 = 1/2 → Together: 2 hours
  • Worker A: 8 items/day, B: 12 items/day → 100 items = 100/20 = 5 days together

So erkennen Sie es

  • Multiple workers/machines working simultaneously
  • Individual rates are given (units per time)
  • Asked for time when working together

Häufige Fehler

  • Averaging rates instead of adding them
  • Adding times instead of rates (if A takes 2hr and B takes 3hr, together is NOT 5hr)
  • Forgetting to convert to consistent rate units

Schritt-für-Schritt-Lösung

Rohr A füllt einen Tank in 4 Stunden. Rohr B in 6 Stunden. Wie lange dauert es zusammen?

  1. Berechne die Rate von Rohr A: 1 Tank / 4 Stunden = 1/4 pro Stunde
  2. Berechne die Rate von Rohr B: 1 Tank / 6 Stunden = 1/6 pro Stunde
  3. Addiere die Raten: 1/4 + 1/6 = 3/12 + 2/12 = 5/12 pro Stunde
  4. Berechne die Zeit: 1 / (5/12) = 12/5 = 2,4 Stunden

Antwort: 2.4 hours (or 2 hours 24 minutes)

Übungshinweise